Join KCA and have access to our Safety and OSHA Information. Just log in.
As a recent example, KCA provided the following OSHA information
to members... and below that, the safety information.
Excavations
Introduction
"Construction contractors must dig trenches not graves".
The Occupational Safety and Health Administration (OSHA) has used
this comment many times in press releases involving citations under
a national emphasis program that focuses on excavations. Too often
workers have entered trenches only to lose their lives in a cave
in. In fact, over 200 workers are killed annually in trench cave
in accidents.
OSHA Activity
The following are some examples of OSHA inspections and citations
for Excavation inspections.
These examples are but a few of the inspections that OSHA has conducted to ensure that excavations are safe for workers. An OSHA inspector can perform an excavation inspection anytime. Contractors must comply with the rules to protect employees and to prevent OSHA citations.
Hazard Control
Hazard control for excavations involves pre-planning, selection
of proper control measures and daily inspections to identify any
changes.
Pre-Planning
The OSHA Standard for Excavations Subpart P (1926.650) provides
detailed information to plan an excavation. A matrix that is found
in Appendix F of the standard summarizes the requirements for excavations
twenty feet or less in depth.
Initially, it must be determined whether or not the excavation will be greater than five feet in depth. If it will be five feet or less, excavation may be made with vertical sides, unless there is a potential for cave in. If the excavation is greater than five feet it may be made with vertical sides only if the excavation is entirely in stable rock. Stable rock is defined as natural solid mineral matter. If the excavation will not be in stable rock, the excavation must be slopped, shored or shielded.
Proper Control Measures
Sloping
Sloping can be used without soil classification only if a slope
of 1 ½ horizontal to 1 vertical can be maintained. Oftentimes
this slope is not feasible so soil classification must be done.
Soil types are classified as follows:
Soil Type A – Most Stable: clay, silty clay, and hardpan (resists penetration)
Soil Type B – Medium stability: silt, sandy loam, medium clay and unstable dry rock.
Soil Type C – Least stable: gravel, loamy sand, soft clay, submerged soil or dense, heavy unstable rock
A competent person must determine soil classification using a visual method and one mechanical method.
Visual Testing
Manual Testing
These tests are detailed in Appendix A of the Excavation Standards.
The maximum allowable slopes for each soil class when the trench is less than 20 feet is as follows:
Soil Type Height/Depth Ratio
- Stable Rock Vertical
- Type A ¾:1
- Type B 1:1
- Type C 1 and1/2:1
For example a 10 foot-deep trench in Type B soil would have to be sloped to a 45-degree angle, or sloped back 10 feet in both directions. In Type C soil, the trench would be sloped at a 34-degree angle, or 15 feet back in both directions.
Excavations or trenches 20 feet deep or greater must have a protective system designed by a registered professional engineer.
Benching
There are two types of benching, single and multiple, which
can be used in conjunction with sloping. In type B soil the vertical
height of the benches must not exceed 4 feet. Benches must be below
the maximum allowable slope for that soil type. A 10-foot deep trench
in Type B soil must be benched back 10 feet in each direction with
a maximum of a 45-degree angle. Benching is not allowed in Type
C soil.
Shoring/Shielding
Shoring or shielding is used when the location and depth of the
cut makes sloping impractical. Shoring involves setting up a structure
that supports the sides of excavations to prevent cave ins. There
are two types of shoring: aluminum hydraulic and timber. Shielding
involves the use of a structure that is able to withstand the forces
imposed on it by a cave-in and thereby protect employees. This equipment
ics commonly referred to as a trench box. Soil classification is
required when shoring or shielding is used. OSHA allows shoring
or shielding using one of four options:
Option 1: Appendices A and C of OSHA Standard 1926.650 outlines the procedures and specifications for Timber Shoring. Appendix A outlines the requirements for soil classification. Appendix C provides Tables that provide specifications for the cross braces, wales and uprights based on the soil type and trench depth.
Option 2: Manufacturer’s data can be used to when using hydraulic shoring, trench jacks, air shores and shields. This information must be kept at the job site while the protective system is being constructed. After that time, the information can be kept off site, but must be made available upon request by an OSHA inspector. Any deviations from the manufacturer data can only be made with the written permission of the manufacturer.
Option 3: The use of other tabulated data from tables prepared by a professional engineer. The tables and other data must be kept at the job site while the protective system is being constructed. After that time, the information can be kept off site, but must be made available upon request by an OSHA inspector.
Option 4: Design of the excavation by a professional engineer. The design must be in written form and shall include a plan describing the materials and equipment to be used and the identity of the professional engineer who designed the plan.
Other Hazards and Controls
While cave in is the hazard most often associated with excavations,
there are other hazards that must be considered.
Hazardous Atmospheres
If there is any possibility that the trench or excavation could
contain a hazardous atmosphere, air testing must be done prior to
entry. Conditions that might warrant testing include if the excavation
takes place in a landfill area or if it is in the vicinity of pipelines
containing a hazardous chemical. Testing should be done periodically
to ensure that conditions have not changed, especially when equipment
is operated in the trench or when welding, brazing or cutting is
done.
Standing Water and Water Accumulation
Some control measures include:
Spoil
Temporary spoil shall be placed no closer than 2 feet from the surface
edge of the excavation, measured from the nearest base of the spoil
to the cut. Place spoil so that it will channel rainwater and other
run-off water away from the excavation. Remove permanent spoil further
away from the excavation
Surface Crossing of Trenches
Surface crossings should not be made unless absolutely essential.
Vehicle crossings must be designed by and installed by a professional
engineer. Walkways or bridges must:
Entry and Exit
Trenches 4 feet or more in depth must have a fixed means
of egress. A worker must be able to access a ladder from a distance
of 25 feet at most from any part of the excavation. Ladders must
be secured and extend a minimum of 36 inches above the landing.
Exposure to Vehicles
Employees exposed the vehicle traffic must wear reflective vests
or other garments. Trained flag persons, signs, signals and barricades
must be used when needed.
Exposure to Falling Loads
Workers in trenches should wear hardhats. Employees must not be
permitted to work under raised loads or other loads being lifted
or moved by heavy equipment.
Mobile Equipment
Warning systems, hand or mechanical signals or stop logs must be
used as necessary to prevent vehicles from falling into the trench.
Competent Person and Inspections
A competent person for the purposes of excavations is
one who is capable of identifying existing and predictable hazards
in the surroundings or working conditions and who has the authorization
to eliminate them. The competent person must have specific training
in soil analysis, the use of protective systems and the OSHA Standards.
Inspections are required:
Conclusion
Excavations pose significant safety challenges. Pre-planning is
a vital part of the OSHA requirements. Soil analysis followed by
the selection of the most effective cave-in control measure will
ensure that workers are properly protected. The competent person
oversees the day to day hazard control program. Constant attention
to changing conditions and the status of hazard control measures
will ensure the ongoing safety of workers.